Start time: 12/19/2013 10:00PM EST
Estimated completion time: 12/26/2013 5:00AM EST
Estimated downtime: 15 minutes per Linux VM, 60 minutes per Windows VM
Synopsis:
As you are aware we recently moved to a new data center which offered increased redundancy and also enabled us to get a new cutting-edge SAN provided by a Tier 1 storage vendor in place. This SAN provides the latest in redundant architecture as well as cutting-edge technology to ensure the highest levels of performance. With that being said, we are excited to inform you that the new SAN is now in place and we will be migrating to it starting this week! Migrations to this new SAN will begin on 12/19/2013 and end on 12/26/2013. To minimize impact the migrations will be performed during the hours of 10:00PM EST and 5:00AM EST.
We thank you for you business and, as always, if you have questions or need assistance please contact our technical support team.